How to switch IT provider without downtime: a 30-day handover plan

The ticket about the shared drive has been open for nine days. The renewal letter arrived this morning. And somewhere between the two, you realise you don’t actually know who holds the admin password for your Microsoft 365, or whose name your domain is registered in.

That uneasy feeling is the real reason most businesses put off switching IT provider. The work itself is rarely the problem. A planned switch takes about 30 days of practical effort inside your notice period, and staff should barely notice it happening. Where switches go wrong is ownership and contracts: a domain registered to the old provider, an admin account nobody else can open, a notice date missed by a week.

This guide shows what to secure before you give notice, how each system moves across, and a week-by-week plan to get from one provider to the next without downtime.

In short:

  1. Secure admin access, your domain and your DNS before you give notice.
  2. Read the contract for the notice period and the auto-renewal date, because that date sets your timetable.
  3. Choose the new provider first, then serve notice with a written handover request.
  4. Run both providers side by side for two to four weeks, with backups overlapping.
  5. Move email and phones out of hours, then remove every trace of the old provider’s access.

Should you switch, or fix what you have?

Switch when the problems are structural rather than a bad month. Repeated missed response times, faults that keep coming back and no security reporting are reasons to leave. A single poor patch is usually worth one formal attempt to fix first, because a switch costs time and goodwill on both sides.

The signs that justify moving are fairly consistent. Your provider misses its service level agreements and nobody reports on them, even though NCSC guidance expects a response within an hour for urgent incidents. The same printer, VPN or email fault returns every few weeks. You never see a backup or security report, which matters more now that cyber insurers ask for evidence. The provider sells you basic protection as an extra, nobody talks to you about next year, and your domain or licences sit in the provider’s name.

If that reads like your situation, you are dealing with reactive IT support, and a review won’t change the model.

If it’s less clear cut, give the relationship one fair test. Check what the SLA actually promises, log the evidence, and ask for a minuted service review with a corrective plan and a date. Escalate in writing if nothing changes, and claim any service credits within the deadline the contract sets.

One thing not to do, however frustrated you are, is cancel the direct debit yourself: it hands the provider a breach argument just when you need it to cooperate.

IT engineers at their laptops checking admin access before a change of IT provider

Before you give notice: find out what you actually own

Before you say anything to your provider, confirm that your business, not the provider, controls the Microsoft 365 admin, the domain, the DNS, the backups and the phone numbers. You can check each of these quietly, and each is far easier to fix while the relationship is still friendly.

You wouldn’t be unusual in having gaps here. The government’s Cyber security breaches survey 2025/2026 found that 64% of small businesses outsource their cyber security, yet only 22% had formally reviewed the risks their immediate suppliers pose. Nearly two in three hand the keys over; about one in five has checked what that means. The joint advisory on managed service providers from the NCSC, CISA and partner agencies makes the exit risk explicit, warning that “disabling MSP accounts can be overlooked when a contract terminates.”

None of the checks below needs to announce that you’re leaving. A neutral request does the job: “We’re updating our asset and supplier records for our insurance renewal. Could you confirm who is the registered owner of our domain, and send us a list of the admin accounts and licences you manage for us?” Most providers answer that without a second thought.

Your Microsoft 365 tenant, admin access and licences

Start here, because this is where a switch can stall for weeks. Before you give notice, create two emergency Global Administrator accounts that only your business controls, often called break-glass accounts. Since Microsoft made multi-factor authentication mandatory for admin access, they need a phishing-resistant method such as a FIDO2 security key or certificate-based sign-in, so set that up properly rather than adding a phone number and hoping.

The reason is what happens without them. If the old provider holds the only admin accounts and won’t hand them over, only Microsoft’s Data Protection team can restore your access. That typically takes 3 to 10 working days if you control your domain’s DNS, and two to four weeks or more if the DNS has to be recovered first. Either figure wrecks a 30-day plan.

Microsoft 365 licences on an annual commitment

Licences are the second part. Most small businesses buy Microsoft 365 through their IT provider, acting as a Cloud Solution Provider (CSP), on Microsoft’s New Commerce Experience. You can only cancel annual NCE subscriptions in the first seven days; after that you pay to the end of the term. They can move to your new provider mid-term through a partner-to-partner transfer, with no downtime and the same price and end date, but the outgoing partner has to approve the transfer and Microsoft won’t override it.

If the old provider refuses, the fallback is to keep paying it for those seats until renewal while the new provider supports you through its own admin relationship.

Two rules save a lot of grief. Never cancel a subscription before the new licences are active. And ignore older guides that promise a free 30-day grace period after a subscription ends: Microsoft removed it on 4 May 2026, so a subscription set to cancel at expiry now stops on the expiry date.

You can see which partners have admin rights in the Microsoft 365 admin centre under Settings, then Partner relationships. Don’t remove anything yet; just note who is listed, as you may find both your provider and its distributor. If you’re on Google Workspace instead, your own super admin issues the transfer authorisation and the reseller can’t block it, though a prepaid annual plan isn’t refunded, so time the move for renewal.

Your domain name and DNS

Paying your IT provider’s invoice for the domain doesn’t make you its owner. Only the registrant recorded with the registry can instruct a transfer, and plenty of providers register client domains in their own name for convenience.

Checking takes a few minutes, though not where most people look. RDAP has replaced public WHOIS lookups for .uk domains, and registrant names stay hidden by default, so the answer sits in your registrar account or in Nominet Online Services. Ask your provider for the registrar’s name and log in, or ask them to confirm the registrant in writing.

How the domain moves depends on its ending:

DomainHow it transfers nowWhat to know
.uk, .co.ukIPS tag change at NominetFrom 9 February 2027 Nominet moves to Transfer Authorisation Codes, valid for 14 days and issued free within five days
.comAuth code (EPP code) from the losing registrarThe registrar must release it within five days and can’t refuse over a payment dispute

Two details catch people out. For .com, a change of registrant details triggers a 60-day transfer lock, which ICANN has agreed to remove but hasn’t yet implemented, so move the registrar first and update the owner details afterwards. And if the provider registered your .uk domain in its own name, recovering it through Nominet’s Dispute Resolution Service takes 8 to 12 weeks. That is why this is a day one check, not a week four one.

Registrar, registrant and DNS host

Separate three things that are often bundled: the registrar (where the domain is registered), the registrant (who owns it) and the DNS host (where the records live). If the old provider hosts your DNS and deletes the zone on its last day, your website, email and phones can all fail at once. Move DNS to an account you own 7 to 10 days before cutover, and lower the TTL values 48 hours before any change so updates spread quickly.

Email filtering and security tools

Email is where most switches go wrong, usually because of a filtering service nobody remembers. If a gateway such as Mimecast or Proofpoint sits in front of Microsoft 365, your tenant will normally have an inbound connector that only accepts mail from that gateway. Change the MX record to point somewhere new without updating the connector, and every external email bounces. Suspend the gateway account before changing the outbound connector, and all outgoing mail stalls.

The safe order is to pre-stage the new filtering (or Microsoft Defender for Office 365 policies), change the connectors and the MX record together, test straight away, and then remove the rule that lets gateway mail bypass spam filtering. While you’re in the DNS, tidy the records that usually lapse: an SPF record that lists every service sending on your behalf, DKIM switched on for Microsoft 365, and DMARC reports going to an address you own rather than the provider’s.

Devices, encryption keys and admin passwords

The device layer holds the small items that cause the biggest headaches. BitLocker recovery keys are the first: if they sit only in the old provider’s remote monitoring and management (RMM) tool, they disappear when the provider removes that tool, and a locked laptop becomes a wiped laptop. Escrow the keys in Microsoft Entra ID, and rotate them after the switch.

Security software comes next. Endpoint detection and response (EDR) tools usually have tamper protection, which is good until the old provider deletes your devices from its console with tamper protection still switched on. Then someone has to clean up each PC in Safe Mode, one by one. Agree with the outgoing provider that it will release the agents properly, and plan the swap out of hours.

Old RMM and remote-control agents need removing even after you disable the provider’s accounts, because they run with SYSTEM-level access to every machine. Replace a shared local admin password across all PCs with Windows LAPS, which sets a unique, rotating password per device. Windows Autopilot device registrations and Apple Business Manager should sit in your own tenant and account; iOS and macOS 26 can migrate devices to a new device management service without wiping them.

Firewalls, Wi-Fi and password vaults

Firewalls and Wi-Fi deserve a check on day one. Find out whether you own or lease the firewall, and who holds the cloud account behind it (FortiCloud, MySonicWall, Meraki or UniFi). A UniFi network without a proper owner transfer can mean factory-resetting every device. Push new Wi-Fi profiles to devices before changing the key, or printers and CCTV will quietly drop off the network.

Password vaults are the last trap. Exports from documentation tools such as IT Glue can mask passwords by default, and deleting a Keeper managed company can wipe staff vaults with it, so export with care and change every admin credential once the new provider is in.

Backups and historical data

Your live data is safe whatever happens: the new provider’s backup protects everything current from its first run. What’s at risk is history, meaning deleted items, older versions of files and the mailboxes of people who have left, which may now exist only in the old provider’s backup.

How long that history survives after cancellation depends on the product:

Backup serviceData kept after cancellation
Datto Endpoint Backup for PCs0 days
Datto SaaS Protection30 days
N-able Cove30 days
Acronis30 days
Datto SIRIS and ALTO cloud60 days
Microsoft 365 BackupStays in your own tenant

Exports generally need an active subscription, so they have to happen before cancellation, not after. The sensible rule is to run both backups for 14 to 30 days, test a restore from the new one before cutover, and export a final image plus leavers’ mailboxes before day 30 if you have legal or regulatory retention duties. Assume you can’t transfer backup history between products unless the vendors confirm otherwise. For a wider view on what your backups should cover, see our guide to business continuity and disaster recovery.

Business desk phone in an office, ready for a phone number port to a new provider

Phone lines, broadband and numbers

If your IT provider also supplies your phone lines, broadband or VoIP system, treat them as a separate move with its own rules, because a lost number costs more than a slow ticket.

Ofcom’s rules give every business customer a baseline. Providers can’t charge you directly for porting your numbers, you can still port them for at least a month after you switch, and any loss of service during the switch mustn’t exceed one working day. The old provider has to keep your service running on the same terms until the switch completes. The stronger protections, including a one-page contract summary, a 24-month cap on commitment periods and renewal only with your consent, apply only to businesses with 10 or fewer employees.

One Touch Switching, the simplified process for home broadband, doesn’t cover business lines, so businesses still switch with an order and a Letter of Authority.

Porting your numbers

The new provider starts the port, never you. Lead times run from about four working days for a single line to 22 to 25 working days for a complex range of direct dial (DDI) numbers, which is why the order should go in during the first week. Ports most often fail on a postcode that doesn’t match the old account, a missing number range, or naming your IT provider instead of the underlying carrier.

An unpaid bill isn’t one of the reasons the industry’s porting process allows for rejecting a port, so a billing disagreement with the old provider shouldn’t stop your numbers moving; settle it separately.

Three practical cautions. Never cancel the old lines before the port completes, or the numbers can be lost. Export call recordings and voicemails, because they don’t travel with the numbers. And if you use Microsoft Teams Phone, remember the numbers belong to whoever provides the calling service, not whoever sold you the licences, so a Calling Plan number can stay with Microsoft even when your CSP changes.

The PSTN switch-off

The timing matters in the West Midlands too. Openreach is moving all analogue phone line users to new services by 31 January 2027, and the government’s timeline lists exchange closures locally, including Beacon by April 2028 and Dudley and Knowle by December 2030. If any of your lines, alarms or card machines still depend on the old network, fold that into the switch rather than handling it twice. Our guide to the PSTN switch-off explains the options, and it’s worth reading the small print on “unlimited” call packages before you sign anything new.

Documentation and line-of-business software

Ask for the asset list, network diagram, runbook and any licence keys the provider holds. Then check that your business is the registered owner of your accounts software, CRM and other line-of-business systems, with someone in your business listed as the admin contact at each vendor.

A good incoming provider will validate this documentation rather than trust it, which is usually where the surprises turn up.

Before you give notice

Who owns what? Check your handover risk

For each item, pick who holds it today. You'll get a red, amber or green rating and the next step to take before you tell your current provider.

0 red 0 amber 0 green

Answer each item to see your overall handover risk.

A guide only, based on common handover problems. Nothing you select is stored or sent anywhere.

Check your contract for the exit terms

Your notice date, not the technical work, decides when you can switch IT provider. Find the minimum term, the notice period, the auto-renewal window and any exit or handover charges before you contact anyone new, because missing the notice date by a day can tie you in for another year.

Managed IT contracts in the UK commonly run for 12 to 36 months, with 30 to 90 days’ notice (90 is common). Many renew automatically for another 12 to 24 months if notice arrives late, and leaving early can cost the full remaining fees. At natural expiry, a good provider hands over without charging for it. Contracts that say nothing about offboarding sometimes bill the work by the hour, typically at £75 to £125.

On your rights, be realistic. The Consumer Rights Act doesn’t protect businesses, and the Unfair Contract Terms Act offers only limited help between companies. Courts have refused to enforce onerous charges that the supplier didn’t properly bring to the customer’s attention, as in Blu-Sky Solutions v Be Caring (2021), but if a large sum is at stake, take legal advice rather than arguing the point by email.

Before you give notice, ask in writing for the contract pack (including how you must serve notice), the licence register, the registrant and DNS details, the runbook and keys, and an inventory of any phone and broadband services.

For what an IT contract should include in the first place, see what an IT support contract should include.

Contract check

When is your last day to give notice?

Enter your contract's end or renewal date and its notice period. The calculator shows the deadline and when to start preparing the switch.

Usually in the contract schedule or on your renewal letter.

90 days is common in managed IT contracts.

Pick your contract end date to see your deadline.

A planning guide, not legal advice. Contracts differ on how notice is counted and served (by email, letter or portal), so check the wording and allow a few days' margin.

Your data and GDPR when you leave

Your outgoing provider is a data processor under UK GDPR, and when the contract ends it must return or delete your personal data, at your choice, and delete its remaining copies. Ask for that in writing, with a date.

The rule is Article 28(3)(g), and the Data (Use and Access) Act 2025 didn’t change it. Backups get a practical allowance: the ICO accepts that the provider can overwrite them in their normal cycle, provided it deletes live copies now and puts the backups beyond use until then.

A provider that holds your data back to apply pressure is in a weak position, because under Article 28(10) a processor that decides for itself what happens to the data becomes a controller for that processing, with the obligations that come with it.

What to ask the outgoing provider to confirm in writing:

  • the return of your data, including call recordings and leavers’ mailboxes
  • deletion of live copies on a stated date
  • the date by which backups will be overwritten
  • the sub-processors that held your data
  • that all of its access to your systems has been removed
Team planning an IT handover with sticky notes on a whiteboard

The 30-day handover plan

Switching IT provider takes two to four weeks of technical work for most small businesses, and four to eight weeks end to end once choosing a provider and the notice period are included. The 30 days below are the working window inside your notice period.

Across the plan, systems move in one order: backups first, then monitoring, then security tools, then email, then phones. Only three moments carry real downtime risk, the security software swap, the email (MX) change and the number port, and each one happens out of hours.

Before day one: secure the keys quietly

Choose and sign with your new provider before you serve notice, so you’re never without support. Our guide on how to choose an IT support provider covers what to look for. In the same window, set up your break-glass admin accounts, confirm who the registered owner of your domain is, make sure you can log in to your DNS, and gather recent phone and broadband bills for the port.

Week 1: give notice and start discovery

  1. Serve notice by the method your contract specifies, with your handover request list attached.
  2. The new provider starts a read-only discovery audit of your systems.
  3. The Letter of Authority for the number port goes in now, because of lead times.

Week 2: validate access and build in parallel

  1. Test every credential the old provider sends rather than trusting the document.
  2. Set up the new CSP relationship and admin access in Microsoft 365.
  3. Start the new backups and test a restore.
  4. Lower DNS TTLs and pre-build phones on temporary numbers.

Week 3: parallel running and the risky changes

The new monitoring agent goes onto devices quietly in the background, and the new provider pilots the security software swap on a few machines out of hours before rolling it out. If email filtering changes, the MX record moves after 18:00 on a Friday, with testing straight away. The number port happens on its agreed date.

Staff hear about the change seven days and two days before go-live, with one warning included: nobody from the new IT team will ever ask for their password by phone or email. Provider switches are a well-known window for phishing calls that pretend to be “the new support desk”.

Week 4: go live, lock down and review

The helpdesk number changes over, and you release the old provider only once the switch passes an acceptance check:

  • you own the break-glass admin accounts and the registrar account
  • backups are green and a test restore has worked
  • at least 95% of PCs and all servers report into the new tools
  • you have changed every admin credential
  • old agents, partner admin access, VPNs and accounts are removed
  • phones are tested, including the emergency services address

Keep an eye on sign-in logs for 30 days afterwards, and hold a short review with the new provider to close off anything left over.

The 30-day plan

Switching IT provider, week by week

Select a stage to see what happens. Red marks the moments with real downtime risk, all scheduled out of hours.

Cutover order:Backups→Monitoring→Security tools→Email→Phones

Typical timings for a small business: two to four weeks of technical work, four to eight weeks end to end including the notice period.

IT engineer working alone in an empty office in the evening during an out-of-hours cutover

Will switching cause downtime?

Planned properly, no. Most staff notice a new support number and a new icon on their PC, and little else. The work happens remotely and out of hours, and the three riskier changes each have a rollback plan.

Those three are the security software swap, the email cutover and the phone number port. The new provider pilots the first on a few devices before the rest, the second happens on a Friday evening with immediate testing, and for the third Ofcom limits lost service during a switch to one working day.

Downtime during a switch almost always traces back to something unplanned, such as a forgotten filtering service or lines cancelled too early, which is exactly what the ownership checks above catch.

What if your current provider won’t cooperate?

Most outgoing providers hand over professionally, and if you’ve secured admin access, the domain and DNS before giving notice, an obstructive one has very little left to hold over you. The NCSC’s advice for ending any supplier contract is direct: “make sure you regain control of your assets and shut down any unauthorised or unintended access to your information and systems.”

Where cooperation does break down, each asset has its own route. For Microsoft 365, Microsoft’s Data Protection team can restore admin access once you prove ownership, slowly, which is why the break-glass accounts come first. For a .uk domain registered in your name, you can move it through Nominet Online Services for £10 plus VAT without the old registrar’s help. A .com registrar must release the auth code within five days whatever the billing position.

Your phone numbers move through the new provider’s port, which a billing dispute shouldn’t block. And your data is covered by Article 28: a provider that withholds it to apply pressure takes on a controller’s responsibilities.

Retained access is a security issue, not just an inconvenience. In 2024 the ICO reprimanded Levales Solicitors after an attacker got in using valid domain admin credentials without multi-factor authentication; the firm had outsourced its IT since 2012 without reviewing the supplier’s security. Keep every request in writing, keep paying what you owe while the handover runs, and take legal advice before withholding any payment.

Questions to ask your new provider about the takeover

Ask the new provider how it will run the handover, not just how it will support you afterwards. These questions focus on the switch itself:

  • Will our domain, Microsoft 365 tenant and admin accounts stay in our name?
  • What exactly do you need from our current provider, and will you ask for it on our behalf?
  • What happens if they’re slow or uncooperative?
  • How do you schedule the email and phone cutover?
  • How do you remove the old provider’s access, and how will you show us it’s gone?
  • If we ever leave you, what happens to our data and our access?

A provider that answers the last question as readily as the first is usually one you can trust with the rest.

Switching IT provider checklist

Neither Microsoft nor the NCSC publishes a customer checklist for leaving a managed service provider, so here is ours, drawn from everything above.

Before notice:

  • Two break-glass Global Admin accounts set up and tested
  • Domain registrant and registrar confirmed, DNS access in your hands
  • Partner relationships in Microsoft 365 noted
  • Contract notice period, method and renewal date confirmed
  • New provider chosen and signed
  • Phone and broadband bills gathered

During handover:

  • Notice served with a written handover request
  • Port order and Letter of Authority submitted in week one
  • Credentials validated, BitLocker keys escrowed in Entra ID
  • New backups running, test restore done, old backups exported if needed
  • Email connectors and MX changed together, out of hours
  • Staff warned about fake “new IT team” calls

After cutover:

  • Old RMM, remote access and security agents removed
  • Old partner access, VPNs and accounts removed
  • Every admin password rotated, Windows LAPS in place
  • Written GDPR confirmation of data return and deletion
  • Sign-in logs watched for 30 days, post-switch review held

How ComputerCentric handles a takeover

When ComputerCentric takes over from another provider, the ownership checks come first: we confirm your admin access, domain, DNS and licences are in your name before anything else moves. We then contact the outgoing provider on your behalf with a written handover request, so you aren’t left chasing passwords.

Because we supply business phone lines and broadband as well as IT support, number ports and line migrations stay with one team instead of being split between suppliers. Cutovers happen out of hours, both setups run side by side until the acceptance checks pass, and we leave every account and asset registered to your business.

You can read more about our business IT support for firms across the West Midlands and Staffordshire, or talk to us about switching.

Switching IT provider: frequently asked questions

How long does it take to switch IT provider?

For most small businesses the technical work takes two to four weeks, and the whole process four to eight weeks once you include choosing a provider and serving notice. In practice your notice period sets the pace, which is why it pays to read the contract before anything else.

Will switching IT provider cause downtime?

Not if it’s planned. Most changes happen remotely and out of hours. The three moments with real risk are the security software swap, the email cutover and the phone number port, and each is scheduled outside working hours with a way back if something doesn’t behave.

Do I need to tell my current provider before talking to a new one?

No. You can speak to new providers and sign with one before giving notice, and you should secure your admin accounts, domain and DNS before your current provider knows you’re leaving. Serve notice only once the new provider is ready to start.

Who owns our Microsoft 365 account when we leave?

Your business owns the tenant and its data, but whoever holds the Global Administrator accounts controls it in practice. Create two emergency admin accounts of your own before giving notice. If the old provider holds the only access, recovering it through Microsoft can take several weeks.

What happens to our Microsoft licences if we’re on an annual commitment?

Annual NCE subscriptions can’t be cancelled after the first seven days, but they can move to your new provider mid-term through a partner-to-partner transfer, keeping the same price and end date. The old provider has to approve it. If it won’t, you keep paying it for those seats until renewal.

Can we keep our phone numbers if we switch?

Yes. Business customers can’t be charged directly for porting, and you can still port for at least a month after switching. Your new provider submits the request, never you, and complex number ranges can take five weeks, so start in the first week. Don’t cancel the old lines until the port completes.

Does it cost anything to switch IT provider?

The main costs come from your existing contract: any fees for leaving early, and handover charges if the contract allows them. Leaving at the natural end of the term with proper notice usually costs nothing beyond paying out the notice period, and a good outgoing provider hands over without charge.

Is switching MSP different from switching IT support company?

No. A managed service provider (MSP) is simply an IT support company that looks after your systems for a monthly fee under a contract, rather than fixing things as they break. Switching MSP follows the same steps described in this guide.

Planning your switch

Switching IT provider is mostly paperwork, but the paperwork has teeth. Secure the admin accounts, the domain and the DNS first, time your notice to the contract, and run both providers side by side until the checks pass. 

Do that, and the switch your team notices is a better helpdesk, not a lost week. If you’d like a second pair of eyes on your contract or your handover, get in touch and we’ll walk through it with you.

Get in Touch

Microsoft Outage – Update

13/11/2026 12:20 Bing! We’re seeing some signs of life in Microsoft 365 email flow and Outlook.com.   13/11/2026 12:15 Some initial thoughts on this… “It

Read More »
Join our mailing list

If you’d like to receive useful information, news and advice to help you stay smart and ahead of the game when it comes to IT in business, then let us know below!  We won’t spam you, and you can opt-out any time.

from the blog